Meet ‘Bill’. He is a stone mason from Halifax and took the time to explain the repairs.

035

 

-         To complete the task he required 4 full good weather days in a row, thus the time delay. (Mark had contacted him several times)

-         The mortar must be repaired correctly; the stones repaired and put in place according to size.  (Mount A has a rock pile)

-         The repairs will involve small steel bars placed in regular locations throughout the sides of the bridge to prevent this from taking place again.

Repairs will be completed by Friday evening or Saturday at the latest.

034

Ta Da!!!!   The finished product.  Looks as good as it was when new 12 years ago.

                         